At a glance
- No date is fixed yet: the Digital Product Passport for stone becomes a duty 18 months after a Commission delegated act under the Construction Products Regulation enters into force, and we found no adopted act1,2.
- From January 2030 the life-cycle global warming potential of all new buildings must be disclosed in their energy certificates; the Commission says EU countries will plan limit values for new buildings from 20303,4.
- Declarations under the new regulation must cover nine more environmental indicators four years after its date of application; by our calculation from a placeholder in the adopted text, that is January 20301,5.
- Of about 318 million tonnes of dimension stone quarried worldwide in one year, about 29% reached the market as products, according to one 2025 estimate6.
What this article covers
No date is fixed yet: the Digital Product Passport for stone becomes a duty 18 months after a Commission delegated act under the Construction Products Regulation enters into force, and we found no adopted act1,2. Our 2026 guide to the Digital Product Passport for natural stone sets out what applies today. This article makes the longer case: the passport itself has no date yet, but the records it may draw on take time to build, and missing origin records can be difficult to reconstruct. What a stone company records now at the quarry face, in the yard and at the factory decides how much work later requests will take.
The law in brief
The passport for construction products, natural stone included, comes from the Construction Products Regulation (CPR), Regulation (EU) 2024/3110, not from the Ecodesign for Sustainable Products Regulation (ESPR)1,7. Article 75 tells the Commission to adopt delegated acts "setting up a construction digital product passport system"1. Under Article 22(7), the manufacturer must make a passport available "by 18 months after the entry into force of the delegated act"1. We found no adopted act in the sources reviewed, so there is no passport date for stone2.
The passport must "correspond to the product type and its unique identification code"1. Manufacturers mark products with the product-type code "and, where available, a batch or serial number"1. So the regulation does not require a passport for each block or slab. The Commission's DPP FAQ states that "there is no general obligation for a product to have a DPP"7.
Today, CE marking and a declaration of performance apply to stone products covered by a harmonised standard, under the previous regulation's rules10. A product family moves to the new CPR once a new harmonised standard is cited under it, and the old regulation is fully repealed only in 20395.
What 2030 marks
2030 matters for building-carbon disclosure and a further phase of environmental indicators, rather than a fixed stone-passport deadline.
All new buildings disclose life-cycle carbon. Under the recast Energy Performance of Buildings Directive (EU) 2024/1275, the life-cycle global warming potential (GWP) of new buildings must be disclosed in their energy performance certificates from January 2028 for buildings over 1,000 m², and from January 2030 for all new buildings3. The Commission describes the calculation as including the "production and transport of construction products"4. Building-carbon calculations increase demand for usable carbon data; project rules determine whether specific or default data are used. More detailed provenance can be requested separately.
Countries plan limit values. The Commission says that by 2027 all EU countries will develop a roadmap for introducing limit values for the life-cycle GWP of all new buildings from 20304. A limit value can constrain a design, not only ask for a number. Where a product has no specific data, designers may use default values; in France the database operator says default data lead to inflated impacts8.
Declarations carry more indicators. Under Article 15(3) of the CPR, a declaration of performance and conformity must cover the four climate-change indicators of Annex II from the date of application, nine further indicators (from ozone depletion to water use) four years after that date, and the remaining six indicators six years after it1. The adopted text consulted uses a placeholder for the application date. The main part of the CPR applies from 8 January 20265; adding four years gives 8 January 2030. This is our calculation, pending a check against the text published in the Official Journal. These rules reach a stone product only once its family has moved to a harmonised specification issued under the new CPR1,5.
What the digital product passport is expected to carry
Article 76(2) of the CPR lists what a construction passport must include1:
- the declaration of performance and conformity, with its environmental indicators;
- the general product information, instructions for use and safety information;
- the technical documentation;
- the label;
- unique identifiers;
- documentation required under other EU law;
- data carriers of key parts that have their own passport.
Article 76(1) requires the information to be "accurate, complete, and up-to-date"1. The passport system must be "compatible with, interoperable with and based upon" the ESPR passport1.
How long the data must be kept. Article 75(2) says the system shall "ensure that the system is accessible for period of 25 years after the last product corresponding to its product type has been placed on the market and that the economic operator makes available the digital product passport for at least 10 years"1. The same paragraph requires procedures for availability after an operator's insolvency or cessation of activity, including a back-up system1. A Commission presentation, which is not the legal text, describes 10 years of availability as the manufacturer's responsibility and a 15-year back-up9. The delegated act will set the detailed arrangements.
The CPR passport list does not itself prescribe quarry-face coordinates or a per-piece custody chain1. Place-of-origin information is already required by the applicable stone standard11; face-level records are a preparation choice unless a buyer's specification requires them.
| Data area | Legal status | Who records it | Basis |
|---|---|---|---|
| Declaration of performance (future: of performance and conformity) | Required now where a harmonised standard applies; part of the future passport | Manufacturer, per product type | 1,10 |
| Denomination: name, petrological family, colour, place of origin | Required by EN 1469 via EN 12440; EN 1467 requires the denomination for rough blocks | Quarry or manufacturer | 11,12 |
| Climate-change indicators (GWP) | Required in the declaration per product type once the family is under the new CPR | Manufacturer, per product type | 1,5 |
| Unique identifier and data carrier | Part of the future passport | Manufacturer | 1 |
| Quarry face, coordinates, extraction date | Not required by the CPR passages reviewed; possible buyer requirement, check the contract | Quarry, at extraction | 1 |
| Chain of custody, quarry to site | Not required by the CPR passages reviewed; possible buyer requirement, check the contract | Each party at each handoff | 1 |
For stone, one question stays open: every block and slab is different, and no source we found says how a "product type" will map to a quarry's blocks, a factory's bundles or a distributor's lots. One DPP review reports a recommendation to track at batch level for low-value items and at item level for premium products13, but that is an academic view, not a rule. The same research literature is still mostly conceptual and names standardisation, integration, costs, governance and privacy as open barriers13.
Why records made today matter later
Some data is hard to recreate
Dimensions can be re-measured and a carbon study redone. Other facts exist only at the moment they happen: which face a block came from, when it was extracted, what it looked like before dressing, and which slabs came from which block. Once a block has been cut and its slabs sold, these facts survive only if someone recorded them. How much history a company has when the passport duty begins depends on when it starts recording and on when the delegated act enters into force.
Carbon data needs a baseline
A product carbon figure needs energy, fuel and transport data allocated to production. For scale, the Natural Stone Institute's industry-wide EPDs give 21.4 kg CO2e per m² of cladding for stages A1–A3, thickness not stated14. One consultancy and programme operator puts the total cost of an EPD at $15,401 to $42,751 and about 20 person-days of work15; that is a vendor figure and indicative only. Start assembling a representative production baseline now, including existing bills and transport records, and agree its reference period with the LCA practitioner. For published stone figures, see our carbon footprint of natural stone article.
Records show where the stone goes
A 2025 paper estimates that of about 318 million tonnes of dimension stone quarried worldwide in 2021, "about 163 million tons (51%) became quarrying waste during the extraction phase"6. Of the roughly 155 million tonnes of blocks that reached processing, about 63.5 million tonnes (41% of plant input) became processing waste, and about 29% of the gross quarried mass reached the market as products6. A trade-press summary of Carlo Montani's world statistics gives the same totals (318, 155 and 91.5 million tonnes) for 202016. The same paper reports quarry recovery rates "typically ranging between 3% and 60%"6. These are world estimates from industry statistics, not measurements of any one quarry. A company that records blocks by face and slabs by block can calculate its own figures.
Each split sits under the quantity it divides: blocks under the gross quarried, products under the blocks.
How to sequence the work
The order below follows how hard each kind of data is to recreate later. It is our recommendation, not a legal requirement; the last column says which parts are duties today.
| Step | What to do | Why in this order | Duty today? |
|---|---|---|---|
| 1 | Keep declarations and test reports per product type in one place | They are the core of the future passport1 | Declaration: yes, where a harmonised standard applies10 |
| 2 | Give every block an identifier at extraction, with face, date and coordinates | Origin is hard to reconstruct later | No; possible buyer requirement |
| 3 | Record the denomination, and dimensions stating the size type (gross, net or commercial) | EN 1467 requires the denomination and distinguishes three sizes12 | Denomination: required for cladding slabs under EN 146911; specified for blocks in EN 146712 |
| 4 | Optionally, photograph each face | Evidence for later questions | No |
| 5 | Link slabs and bundles to the parent block at the factory | The link is lost once slabs are sold | No; possible buyer requirement |
| 6 | Assemble an energy, fuel and transport baseline from existing records | Needed for any product carbon figure | No; building rules create demand3 |
| 7 | Map every handoff and agree with partners how records are exchanged and maintained | Each undocumented transfer is a gap | No |
Example. Assumptions: a quarry extracts 15 blocks per working day over 250 working days. That is 3,750 block records a year, and about 15,000 after four years, if each record is made at extraction. The same quarry trying to reconstruct origin for its stock later would be working from delivery notes and memory.
What not to do
- Do not wait for the delegated act to choose an identifier approach. Choose a durable identifier and agree how partners will exchange and maintain the record.
- Do not promise customers a passport date. We found none in the sources reviewed2.
- Do not treat the passport as the only reason to record. Building-carbon calculations3,4 already create demand for carbon data.
Frequently Asked Questions
When will the Digital Product Passport be mandatory for natural stone?
No date is fixed. The CPR passport duty starts 18 months after a Commission delegated act under Article 75 enters into force, and we found no adopted act in the sources reviewed1,2. Until then, CE marking and a declaration of performance apply to stone covered by a harmonised standard10. A firm year for stone in any article is a guess.
Is 2030 a deadline for the stone passport?
No. From January 2030 all new EU buildings must disclose life-cycle global warming potential, and the Commission says national limit values for new buildings are planned from 20303,4. By our calculation from a placeholder in the adopted CPR text, it is also when declarations under the new CPR must cover nine further indicators, for product families that have moved to the new regime1,5.
Does the passport come from the ESPR?
No. The ESPR introduces passports product group by product group, and the Commission's FAQ says there is no general obligation for a product to have one7. The construction passport comes from Article 75 of the CPR, which requires the system to be compatible with, interoperable with and based upon the ESPR passport1.
Will the passport record which quarry face a block came from?
The CPR passport list does not prescribe it. Article 76 lists the declaration of performance and conformity, product information, technical documentation, the label, identifiers and other EU documentation1. The stone standards require a place of origin, not a face11. Face-level records are a preparation choice unless a buyer's specification requires them.
How long must passport data be kept?
The CPR says the passport system must be accessible for 25 years after the last product of a type is placed on the market, and the economic operator must make the passport available for at least 10 years1. A Commission presentation describes 10 years by the manufacturer and a 15-year back-up9. The delegated act will set the detailed arrangements.
How Noria Strata handles this
Noria Strata records each block at extraction: a LiDAR scan with the phone for dimensions, GPS coordinates and zone or face attribution, photographs of each face, and the extraction date. The same record carries through to slabs, with each handoff recorded against the same identifier and QR codes giving each party its own level of access. A facility-level carbon baseline links to extraction and processing data. The data structure follows the CPR delegated act as it develops. See the Digital Product Passport in Noria Strata and extraction records.
Sources
- European Parliament and Council (2024). Regulation laying down harmonised conditions for the marketing of construction products, adopted text PE-CONS 12/1/24 REV 1, published as Regulation (EU) 2024/3110 (Articles 15(3), 22(5), 22(7), 75, 76; Annex II) data.consilium.europa.eu/doc/document/PE-12-2024-REV-1/en/pdf
- DIBt (Deutsches Institut für Bautechnik). Transitional rules for the ETA route (FAQ) dibt.de/en/service/faqs/transitional-rules-for-the-eta-route
- European Commission, DG ENER. Energy Performance of Buildings Directive (Directive (EU) 2024/1275) energy.ec.europa.eu/topics/energy-efficiency/energy-performance-buildings/energy-performance-buildings-directive_en
- European Commission, DG ENER. Global warming potential of buildings energy.ec.europa.eu/topics/energy-efficiency/energy-performance-buildings/energy-performance-buildings-directive/global-warming-potential-buildings_en
- European Commission, DG GROW. CPR 2024 revision single-market-economy.ec.europa.eu/sectors/construction/construction-products-regulation-cpr/cpr-2024-revision_en
- Madear, C. & Madear, G. (2025). Minimisation of waste, water and energy consumption at extraction of dimension stone to support eco-label certification. Revista Minelor – Mining Revue 31(2): 84–91. DOI 10.2478/minrv-2025-0021 reference-global.com/download/article/10.2478/minrv-2025-0021.pdf
- European Commission. Digital Product Passport – Explore our FAQs single-market-economy.ec.europa.eu/single-market/digital-product-passport/explore-our-faqs_en
- INIES / Alliance HQE-GBC (2024). Baromètre INIES 2024 inies.fr/wp-content/uploads/2024/07/BAROMETRE-INIES-2024-VD-1.pdf
- European Commission, DG GROW H.1 (c. 2025). The DPP in the new CPR – Regulation (EU) 2024/3110 (presentation by Oscar Nieto at a UNE event; not the legal text) en.une.org/normalizacion_documentos/DPP-in-the-new-CPR---Oscar-Nieto.pdf
- BRE (2013). Guide to testing and CE Marking requirements for natural stone, KN5317 files.bregroup.com/bre-co-uk-file-library-copy/filelibrary//CE%20Marking/KN5317_-_CE_Marking_of_Stone.pdf
- CEN (2015). EN 1469:2015 Natural stone products – Slabs for cladding – Requirements, clause 4.2.2 (preview pages) cdn.standards.iteh.ai/samples/34684/02005aadbe8a4ef4b70c107b6d0f12cc/SIST-EN-1469-2015.pdf
- CEN (2022). EN 1467:2022 Natural stone – Rough blocks – Requirements, clauses 3.2–3.4 and 4.2.2 (preview pages) cdn.standards.iteh.ai/samples/72591/b25b7404e3cb4139b24cb91ca3cfd48c/SIST-EN-1467-2022.pdf
- de Morais, L. C., Silveira, C. E., Mintchev, M. et al. (2026). Exploring the role of DPPs in smart circular economy: a conceptual synthesis. Lecture Notes in Mechanical Engineering (GCSM 2025): 296–304. DOI 10.1007/978-3-032-21154-5_33 research.chalmers.se/publication/552454/file/552454_Fulltext.pdf
- Natural Stone Institute. Embodied Carbon and Natural Stone naturalstoneinstitute.org/programs/sustainability/embodied-carbon-and-natural-stone
- Circular Ecology (n.d.). How much does it cost to produce an EPD? (vendor and EPD programme operator) circularecology.com/how-much-does-it-cost-to-produce-an-epd.html
- Stone-Ideas.com (2021). Dr. Carlo Montani: statistics world stone market 2020 (trade press summarising Montani's XXXII report) stone-ideas.com/90089/dr-carlo-montani-statistics-world-stone-market-2020
How to cite this article
Konstantinou, M. (2026). Digital product passports for stone: 2030 and what to record now. Noria Strata. https://www.noriastrata.com/en/blog/digital-product-passports-2030
The author
Maria KonstantinouCTO, Noria Strata