16 bathrooms, 64 line items. And nobody looks for anything.
1Day 1
Every bathroom, measured on the phone.
The measurer goes through the 4th floor room by room. Vanity top, apron, shower tray, sill: every line item is recorded with its dimensions and its drawing.
2Day 3
Every line item gets its slab.
From stock, 11 slabs of bundle 27 are reserved for the floor. You see where every piece falls, so the veins run on from the vanity top into the apron.
3Day 9
The delay shows before it comes.
12 aprons are waiting for the CNC bridge saw: at this pace the floor is 6 days late. Strata AI says so today, and the aprons go into tomorrow's 2nd shift.
4Day 14
The crew closes the line item with a photo.
In room 409 the installer sees their line items and the drawing on the phone. They fit, photograph, close. At the office, the line item turns green.
5Day 21
64 line items, on time.
The 4th floor is handed over. The customer followed the progress from their link, with photos of every line item, without a single call.